Representative Construction Scheduling Experience
Real scheduling challenges, practical approaches and lessons drawn from more than 29 years of project-controls experience.
Discuss Your Project →The examples below reflect experience led by Pathline’s founder. Client identities and confidential project details are intentionally omitted.
Josh began his career working on his tools in the field before moving into scheduling and project controls. That hands-on foundation gives Pathline an understanding of construction from both sides: how the work is actually executed and how it must be planned, sequenced, measured and communicated through the schedule.
Managing a 50,000+ Activity Turnaround Schedule
A light hydrocarbon unit turnaround on the Gulf Coast: more than 50,000 Primavera P6 activities executed in a roughly 40-day window.
Read ExperienceScheduling a 90-Day Emergency LNG Outage
A 90-day unplanned emergency outage at a Gulf Coast LNG export facility, with all three trains worked in sequence and $100M in outage work.
Read ExperienceScheduling Repeat Ethylene Unit Outages
Numerous ethylene unit outages for a major Gulf Coast petrochemical producer, each running 35 to 45 days with $30M to $80M in outage work.
Read ExperienceShift-Based Earned Progress & Reporting
Experience establishing shift-based earned progress, manpower and schedule reporting for fast-moving construction execution.
Read ExperienceTurning a Baseline Into a Field Execution Plan
Experience translating contract milestones, procurement and field sequence into a maintainable Primavera P6 baseline schedule.
Read ExperiencePut the Schedule to Work
Tell us what you are building, where the project stands, and what the schedule needs to accomplish.